1 .. _text_based_def_using_dependencies_together:
2
3 Using dependencies together
4 ///////////////////////////
5
6 The way a combination of different dependencies work together is not
7 always clear. In order for a node to be scheduled:
8
9 - **Parent**: must be free in order for its children to run. A family must be free before any of its tasks can run.
10 - **Date**: must be free. This is checked when you begin a suite begin(CLI) and at midnight for the suite. There is no midnight for a hybrid clock.
11 - **Time**: must be free. This is checked every minute (configurable.)
12 - **Trigger**: must be free. This is checked every time there is a state change in the suite for all potential nodes.
13 - **Limit**: must not be full. Boolean limits just have slots in them, while integer limits must have enough space for the usage.
14
15 Here are a few examples of combinations with their behaviour.
16
17 To run task only once, on 17th of February 2012 at 10 am:
18
19 .. code-block:: shell
20
21 task x
22 time 10:00
23 date 17.2.2012
24
25
26 To run task twice, at 10am and 8pm, on both 17th and 19th of February
27 2012, that is, four times in all. Notice the task is queued in between,
28 and completes only after the last run. Under a hybrid clock, the task is
29 run (twice) only if the date is either 17th or 19th at the time the
30 suite begins:
31
32 .. code-block:: shell
33
34 task x
35 time 10:00 ; time 20:00
36 date 17.2.2012 ; date 19.2.2012
37
38 To run task after task is complete and if the day is Monday. If the
39 suite is using a real clock, the task waits for the following Monday
40 (unless today is Monday) and for task to be complete. Under a hybrid
41 clock, if today is not Monday when the suite begins or is
42 auto-restarted, task is marked complete without being submitted:
43
44 .. code-block:: shell
45
46 task y
47 task x
48 trigger ./y == complete
49 day monday
50
51
52 The next example shows how to run a task after an earlier task has
53 stopped, either by completing or aborting. It may be useful to continue
54 after a task has tried a few times but still failed. However, this
55 technique should only be used if there is logic somewhere to correct for
56 the missing task. Otherwise, task **y** will fail as well.
57
58 .. code-block:: shell
59
60 task x
61 task y
62 trigger ./x == complete or ./x == aborted
63 #
64 #The above trigger using named operators:
65 #
66 # trigger x eq complete or x eq aborted
67 #
68 task z
69 trigger (x==complete or x==aborted) and (y==complete or y==aborted)
70
71 To run a task on a series of given days, use the Python API:
72
73 .. code-block:: python
74
75 t = ecflow.Task("x")
76 for i in [ 1 , 2, 4, 8, 16 ] :
77 t.add_date(i,0,0) # 0 means any day,month or year
78
79 Will be displayed by the show(CLI) command as:
80
81 .. code-block:: shell
82
83 task x
84 date 1.*.*
85 date 2.*.*
86 date 4.*.*
87
88 To run a task half after the previous task fc has done half of its work:
89
90 .. code-block:: shell
91
92 task fc
93 meter hour 0 240
94 task half
95 trigger fc:hour >= 120
96 # trigger fc:hour ge 120
97
98
99 There is no guarantee that a task will be sent at the exact moment
100 requested. At the specified time, ecFlow might be busy processing other