1 .. _text_based_def_day:
2
3 day
4 ///
5
6 This defines a day dependency for a current node. The parameters are the
7 names of weekdays (lowercase): **sunday, monday, tuesday, wednesday,
8 thursday, friday** or **saturday** . Any combination is acceptable.
9 Names must be typed in full and at least one must be given. Giving the
10 same weekday more than once is not treated as an error. The names can be
11 shortened as long as there is no ambiguity.
12
13 There can be multiple day dependencies, but it is more convenient to
14 define just one dependency, listing the weekdays the node is to run.
15
16 Combined with a date, you can specify more particular dependencies such
17 as the first Monday in a month:
18
19 .. code-block:: shell
20
21 task x
22 date 1-7.*.* # This will not work
23 day monday
24
25
26 Will be listed by the show as
27
28 .. code-block:: shell
29
30 task x
31 date 1.*.*
32 date 2.*.*
33 ...
34 date 7.*.*
35 day monday
36
37 Since the number of days in a month varies, there is no direct means to
38 specify, say, every last Sunday of each month. A list of dates must be
39 provided. If a hybrid clock is defined, any node held by a day