1 <sect2 id="description21"><title>Description</title>
2 <para>
3 The Project performance view is a project management chart where can be understood the actual situation of the project according to the Earned Value Method.
4 </para>
5 <para>
6 <screenshot>
7 <screeninfo></screeninfo>
8 <mediaobject>
9 <imageobject>
10 <imagedata fileref="plan_project_perf_chart.png" format="PNG"/>
11 </imageobject>
12 <textobject>
13 <phrase></phrase>
14 </textobject>
15 </mediaobject>
16 </screenshot>
17 </para>
18 <para>where:
19 </para>
20 <itemizedlist>
21 <listitem><para>BCWS means Budgeted Cost Work Scheduled,</para></listitem>
22 <listitem><para>BCWP means Budgeted Cost Work Performed,</para></listitem>
23 <listitem><para>ACWP means Actual Cost Work Performed.</para></listitem>
24 </itemizedlist>
25 <para>All these are considered as effort in hours and costs.
26 </para>
27 <para>PI are the Performance Indexes, where:
28 </para>
29 <itemizedlist>
30 <listitem><para>CPI is the Cost Performance Index,</para></listitem>