Description
The Task Status View is used to inspect task progress information at a period, set in the configuration.
The tasks are divided into groups dependent on the status of the task:
Not StartedTasks that should have been started by now.RunningTasks that have been started, but not yet finished.FinishedTasks that were finished in this periodNext PeriodTasks that are scheduled to be started in the next period.Editing dataProgress information can be edited in-line as described here or by using the task progress dialog.The following columns are displayed as default:
ColumnDescriptionNameThe name of the task.StatusTask status% CompletionTask completionPlanned EffortThe amount of work planned to be used at the end of the current period.Actual EffortThe amount of work spent.Remaining EffortThe remaining effort needed to complete the task.Planned CostThe planned cost at the end of the current period.Actual CostThe actual cost incurred.Actual StartThe actual start time of the task.Actual FinishThe actual finish time of the task.ConfigurationUsing the context menu, the view can be configured to split / unsplit the tree view or it can be configured using the configure dialog.
The configure dialog enables you to tailor the amount of information the view displays to fit your needs.