Description
The Resource Editor is used to create, edit, and delete resources and resource groups. Resources must belong to a resource group. At the moment sub-groups are not allowed.
Working resources must refer to a calendar that defines the working hours for the resource. Calendars are created using the Work and Vacation Editor.
Material resources are by default always available. You can use a calendar to limit its availability.
Resources can be Shared or Local. A local resource is only used in the current project. A shared resource can be shared between multiple projects and is stored in a separate file, see Managing Resources.
ToolbarThe toolbar provides the means to create and delete resources and resource groups:
ButtonShortcutDescriptionAdd Resource Group&Ctrl;IButton to create a resource group. The new group is appended at the end of the groups.Add Resource&Ctrl;&Shift;IButton to create a resource. The new resource is appended as a child to the currently selected group. If a resource is selected, the new resource is appended to its parent group.DeleteDeleteDeletes the selected resources and/or resource groups.Resources can be created by dropping data from any application that supports dragging vCard information, like KAddressBook or Evolution.
Resources can be copied or moved to a different resource group using drag-and-drop.
When moving a resource, the resource will lose any allocations.Editing dataData can be edited inline as described here.
Resources can also be edited using the Resource Settings Dialog.
The following columns are displayed as default:
ColumnDescriptionNameThe name of the resource or resource group.ScopeA resource can be Shared or Local. A shared resource cannot be edited.TypeThe type of resource or resource group.InitialsThe initials of the resource.EmailThe e-mail address of the resource.CalendarThe calendar defines when the resource is working.Limit (%)The maximum load that can be assigned.Available FromDefines when the resource is available to the project.Available UntilDefines when the resource is available to the project.Normal RateThe cost per hour, normal hours.AccountThe account where the resource cost is accumulated.ConfigurationUsing the context menu, the view can be configured to split/unsplit the tree view or it can be configured using the configure dialog.The configure dialog enables you to tailor the amount of information the view displays to fit your needs.