<sect3 id="introduction0"><title>Introduction In project management, terms may be used in different ways in different programs or different companies or project types. Looking at more exhaustive project management glossaries, one will find alternative definitions for most terms. This list defines how certain terms are used in Plan. Terms Account An account is used in a Cost Breakdown Structure (CBS) to represent a place where cost from tasks or resources can be aggregated. ACWP Actual Cost of Work Performed Actual Cost of Work Performed The actual cost (or effort) that has been performed. Allocation Tasks are allocated to Resources during the planning stage of the project. The actual assignment is done during scheduling. Note that assignment is not guaranteed as the resource may not be available. Assignment Tasks are assigned to Resources during scheduling. BCWS Budgeted Cost of Work Scheduled Budgeted Cost of Work Scheduled The cost (or effort) that should have been used in order to reach the stated progress. BCWP Budgeted Cost of Work Performed Budgeted Cost of Work Performed The cost (or effort) that has been performed. CBS Cost Breakdown Structure CPI Is the Cost Performance Index and is equal to BCWP/ACWP. When this index is below 1, means that you are over budget. If the index is greater than 1 means that the costs are under budget. Cost Breakdown structure The CBS organizes accounts into a structure to enable cost to be aggregated independent of the WBS and RBS. Estimate The estimate is the expected amount of effort or time needed to complete a task. Milestone A milestone is a task with an effort of 0.00h. It is typically used to mark a major outcome, for example the completion of a deliverable upon customer acceptance. PERT Program Evaluation and Review Technique Program Evaluation and Review Technique The Program Evaluation and Review Technique is an enhancement to the Critical Path Method. Task effort estimates in CPM are point estimates, while task effort estimates in PERT are computed by weighting the Optimistic, Most Likely, and Pessimistic estimates (O+(4*M)+P)/6. PERT Distribution A simplified way to calculate Expected estimate from Optimistic-, Most Likely- and Pessimistic estimate. RBS Resource Breakdown Structure Resource Breakdown Structure The RBS organizes resources into resource groups. Resource A resource can be of type Work, Material or Team. A resource must always belong to a Resource Group. Resource Group A resource group is used to group similar resources. Resource Team A resource team is a resource that consists of a number of other resources. SPI Is the Schedule Performance Index and is equal to BCWP/BCWS. When this index is below 1, means that you are behind schedule. If the index is greater than 1 means that you are ahead of the schedule. Summary Task A Summary Task has subordinate Sub-Tasks, and rolls up information based on the Sub-Tasks. Task A Task is a unit of work. Resources are generally allocated at the Task level. vCard vCard is a file format standard for electronic business cards. WBS Work Breakdown Structure Work Breakdown Structure The WBS is used to break down large projects into manageable chunks to ease planning and management.